Grinding • Henderson • 5,000 sq ft
5,000 Sq Ft Coating Removal — Henderson Warehouse
Failing industrial epoxy across an operating distribution warehouse, removed in phases at night so the tenant kept shipping every day.
- Service
- Grinding
- Size
- 5,000 sq ft
- Area
- Henderson
- Scope
- Prep only — no coatings sold
The problem
A 5,000 square foot section of warehouse floor had a delaminating epoxy coating, decades of line striping, and forklift wear that had worn through to bare slab in the traffic lanes. The new coating manufacturer required removal to bare concrete at a CSP 4 profile, and the tenant could not shut down — racking stayed in place and shipping ran every weekday morning.
Scope of work
- Mechanical removal of failed epoxy and line striping across 5,000 sq ft
- Removal of patched trench repairs and old adhesive at the former office footprint
- Profiling the full area to CSP 4 per the coating manufacturer's data sheet
- Detail grinding around racking legs, columns, dock doors, and floor drains
- Four-phase night schedule with each phase handed back walkable by 6:00 AM
- Profile verification against comparison chips at each phase boundary
Equipment used
- Ride-on grinder with multi-head planetary array for open field work
- Dual 30" walk-behind grinders for perimeter passes and phase edges
- PCD and aggressive metal-bond segments for coating removal
- Trailer-mounted HEPA extraction with tandem pre-separators
- Scarifier for the heavy patch and trench areas
The result
All four phases delivered on schedule with no lost shipping days. Profile came in consistent at CSP 4 across every phase boundary, and the coating contractor mobilized the following week with no rework or re-prep.
Job site gallery




Before / after


More work
Other recent projects
Thinset Removal
1,200 Sq Ft Thinset Removal — Las Vegas
View projectTrip Hazard
HOA Sidewalk Trip Hazard Grinding — Summerlin
View projectEpoxy Prep
Garage Epoxy Prep — North Las Vegas
View project
Similar job?
Get a scoped bid on your slab
Send square footage, what's coming off the floor, and your install date — contractors can request trade pricing on the contractor page.